PINE GLADES TUNNEL
Westwood Curtis Construction excavated and installed a 980-foot tunnel beneath Snow King Mountain Resort to provide access to a newly developed subdivision in Jackson, Wyoming. Due to an accelerated design timeline, Westwood Curtis was engaged early in the process to provide value engineering and construction planning support.
Project highlights include:
Excavation and installation of a 980-foot tunnel beneath Snow King Mountain Resort
Early involvement in value engineering to determine construction methods and feasibility
Coordination on precast tunnel dimensions, sequencing, and scheduling
Excavation reaching depths of up to 80 feet below existing grade
Execution under complex geotechnical and access conditions
Commendation from OSHA inspectors for safety procedures and compliance
This project demonstrates Westwood Curtis’s capability to manage deep, technically complex tunnel construction while maintaining high safety standards and schedule coordination.