Ralph Wenz Airport Drainage Improvements (2010)
Westwood Curtis Construction completed stormwater control upgrades at Ralph Wenz Airport in 2010.
Project highlights include:
Installation of approximately 850 feet of arched culvert
Construction of manholes and diversion structures
Phased construction to maintain airport operations
Completion within a 20-day construction window
Careful scheduling ensured uninterrupted aircraft movement throughout the project.